Isaca Certified Information Systems Auditor CISA Question # 346 Topic 35 Discussion

Isaca Certified Information Systems Auditor CISA Question # 346 Topic 35 Discussion

CISA Exam Topic 35 Question 346 Discussion:
Question #: 346
Topic #: 35

The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed. Which of the following should the audit manager do FIRST?


A.

Determine where delays have occurred


B.

Assign additional resources to supplement the audit


C.

Escalate to the audit committee


D.

Extend the audit deadline