Question #: 320
Topic #: 33

Users are complaining that a newly released enterprise resource planning (ERP) system is functioning too slowly. Which of the following tests during the quality assurance (QA) phase would have identified this concern?


A.

Stress


B.

Regression


C.

Interface


D.

Integration


Get Premium CISA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.