Isaca Certified Information Systems Auditor CISA Question # 228 Topic 23 Discussion

Isaca Certified Information Systems Auditor CISA Question # 228 Topic 23 Discussion

CISA Exam Topic 23 Question 228 Discussion:
Question #: 228
Topic #: 23

A month after a company purchased and implemented system and performance monitoring software, reports were too large and therefore were not reviewed or acted upon The MOST effective plan of action would be to:


A.

evaluate replacement systems and performance monitoring software.


B.

restrict functionality of system monitoring software to security-related events.


C.

re-install the system and performance monitoring software.


D.

use analytical tools to produce exception reports from the system and performance monitoring software