Which of the following is the BEST indication that a software development project is on track to meet its completion deadline?
Technical specifications and development requirements have been agreed upon and formally recorded.
Project plan due dates have been documented for each phase of the software development life cycle.
Issues identified during user acceptance testing (UAT) have been addressed prior to the original implementation date.
The planned software go-live date has been communicated in advance to end users and stakeholders.