CISA Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

In a large organization, IT deadlines on important projects have been missed because IT resources are not prioritized properly. Which of the following is the BEST recommendation to address this problem?


A.

Revisit the IT strategic plan.


B.

Implement project portfolio management.


C.

Implement an integrated resource management system.


D.

Implement a comprehensive project scorecard.