Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Isaca Certified Information Systems Auditor CISA Question # 17 Topic 2 Discussion

Isaca Certified Information Systems Auditor CISA Question # 17 Topic 2 Discussion

CISA Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

An IS auditor finds that the cost of developing an application is now projected to significantly exceed the budget. Which of the following is the GREATEST risk to communicate to senior management?


A.

Noncompliance with project methodology


B.

Inability to achieve expected benefits


C.

Increased staff turnover


D.

Project abandonment


Get Premium CISA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.