Question #: 119
Topic #: 12

An IS auditor discovers that an IT organization serving several business units assigns equal priority to all initiatives, creating a risk of delays in securing project funding Which of the following would be MOST helpful in matching demand for projects and services with available resources in a way that supports business objectives?


A.

Project management


B.

Risk assessment results


C.

IT governance framework


D.

Portfolio management