During a project to improve efficiency at a customer service center, the product owner has established that a 15% improvement on a set of 5 measures is the target for a particular initiative. They meet this goal and move on to a new initiative. If they had not moved to a new goal, what agile analysis principle would they be ignoring?


A.

Determine if the need is satisfied


B.

Avoid waste


C.

Think as a customer


D.

Recommend advancing initiative