CCBA Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?


A.

A change management system


B.

A repository


C.

Requirements register


D.

A project scope statement