IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 77 Topic 8 Discussion

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 77 Topic 8 Discussion

CCBA Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

An organization has two different solutions to grow its business. One project is worth $375,000 to the organization. The second project is worth $565,000 to the business. The organization can only do one of the projects and elects to do the second project for $565,000. What is the opportunity cost of this decision?


A.

$190,000


B.

$565,000


C.

$375,000


D.

$940,000


Get Premium CCBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.