Question #: 69
Topic #: 7

A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the first activity the BA performs to understand the effect of the proposed change is to:


A.

determine whether stakeholders are available for further elicitation.


B.

consult with the technical team for technical feasibility.


C.

determine whether the additional requirement is traceable to a need.


D.

check with the project manager for timeline and budget metrics.