New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 134 Topic 14 Discussion

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 134 Topic 14 Discussion

CCBA Exam Topic 14 Question 134 Discussion:
Question #: 134
Topic #: 14

Which of the following is an output of the Identify Stakeholders process?


A.

Scope baseline


B.

Project charter


C.

Stakeholder register


D.

Project scope statement


Get Premium CCBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.