CCBA Exam Topic 14 Question 134 Discussion:
Question #: 134
Topic #: 14

Which of the following is an output of the Identify Stakeholders process?


A.

Scope baseline


B.

Project charter


C.

Stakeholder register


D.

Project scope statement