IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 131 Topic 14 Discussion

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 131 Topic 14 Discussion

CCBA Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor. Which of these stakeholders will be responsible for writing the project scope?


A.

Business analyst


B.

Project manager


C.

Domain subject matter expert


D.

Sponsor