Question #: 128
Topic #: 13
The task of verifying requirements is used to ensure that the requirements are ready for formal review and validation by the customers and for what other purpose?
A.
For defining the specifications for the desired future state based on the solution
B.
For gaining approval of chartering the project
C.
For defining the information to allow additional work to be performed
The task of verifying requirements is used to ensure that the requirements are ready for formal review and validation by the customers and for defining the information to allow additional work to be performed. This means that the requirements are checked for quality attributes such as clarity, completeness, consistency, testability, and traceability. The verification process also helps to identify any gaps, issues, or dependencies that need to be resolved or addressed before proceeding to the next phase of the business analysis work.
References: The information is aligned with the competencies and knowledge areas defined in the Business Analysis Body of Knowledge® (BABOK® Guide) and the Certification of Capability in Business Analysis™ (CCBA®) as provided by the International Institute of Business Analysis (IIBA®). For detailed references, please consult the CCBA® guide1 and the BABOK® Guide2 available through the IIBA® website and bookstore3. You can also find some useful resources and sample questions from other sources45.