Question #: 95
Topic #: 10

Jason is creating a business case for his organization and management has asked him to assess the appropriate risks in the business case regarding the solution. Which one of the following risks is not a concern for Jason when defining the business case and associated risks?


A.

Financial risk


B.

Positive risk


C.

Organizational risk


D.

Technical risk