The plan business analysis activities process involves defining the tasks and resources needed to perform the business analysis work. The inputs to this process are the business analysis approach, the organizational process assets, the stakeholder list, roles, and responsibilities, and the business analysis performance assessment. The list of identified risks is not an input to this process, but rather an output of the identify risks process, which is part of the business analysis planning and monitoring knowledge area. References: BABOK Guide v3, page 37; CBAP / CCBA Certified Business Analysis Study Guide, page 75.