Question #: 111
Topic #: 12

A business analyst (BA) has recently completed a comprehensive stakeholder analysis. Next the BA would like to consider ways in which to ensure that the stakeholders remain engaged throughout the change strategy. Some of the considerations include timing and frequency, location, available tools, delivery methods and the stakeholders' preferences. In which of the following plans would the BA document these considerations?


A.

Stakeholder Collaboration Plan


B.

Business Analyse Plan


C.

Stakeholder Analysis Plan


D.

Communications Management Plan