An internal auditor concluded that delays in an ongoing construction project have cost the organization $10 million to date. Which documents should be included in the audit workpapers to provide sufficient evidence to support the conclusion?


A.

Payment and work milestones


B.

Pictures from the construction site


C.

Initial sprint planning


D.

Project internal rate of return