What are the four phases of project management related to control self-assessment?


A.

Analyzing, Planning, Developing and Reporting


B.

Analyzing, Planning, Accountability and Reporting


C.

Planning, Analyzing, Developing and Changing


D.

Planning, Developing, Reporting and Follow-up