Question #: 57
Topic #: 6

An enhancement project does not change the functional sizing of the application, but just the GSCs. The application's aAFP was 101 FPs, with a VAF of 1.01. The following generic system characteristics are changed as described: a) Flexible query and report facility was provided that can handle simple requests; now this facility can handle complex requests b) Business control data was kept in tables that are maintained by the user with on-line interactive processes, but changes take effect only on the next business cycle; now changes can take effect immediately What is the aAFPA?


A.

100


B.

101


C.

104


D.

106


Get Premium I40-420 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.