IFMA Certified Facility Manager CFM Question # 57 Topic 6 Discussion

IFMA Certified Facility Manager CFM Question # 57 Topic 6 Discussion

CFM Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor’s project estimate is over budget and contingency. What should be done first to address the issue?


A.

Investigate delaying a portion of the project until additional funding is available.


B.

Pursue a change order from the project sponsor for the difference.


C.

Remove the infrastructure upgrade items from the project scope.


D.

Investigate the reasons for being over budget.