New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

IFMA Certified Facility Manager CFM Question # 21 Topic 3 Discussion

IFMA Certified Facility Manager CFM Question # 21 Topic 3 Discussion

CFM Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

A project sponsor indicates that a project should build a facility at the lowest cost, in the least time, and with the highest quality. What should the project manager do?


A.

Work with the sponsor to refine the project charter with more feasible constraints


B.

Implement the project with the given constraints, as instructed by the project sponsor


C.

Inform the project sponsor that a lower-quality project will be provided


D.

Inform the project sponsor that the project cannot proceed with the given constraints


Get Premium CFM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.