IASSC Lean Six Sigma – Black Belt ICBB Question # 85 Topic 9 Discussion

IASSC Lean Six Sigma – Black Belt ICBB Question # 85 Topic 9 Discussion

ICBB Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

The primary objective in removal of waste is to improve the Order Production Cycle where the time from _________________ to the time of receipt of payment is compressed.


A.

Shift start


B.

Product development


C.

Receipt of an order


D.

New fiscal year