The same network slicing scheme is used for the low-voltage power consumption information collection slice and the precise load control slice. (True or False, 2 points)
Question analysis: The collection of low-voltage power consumption information belongs to the mMTC scenario, and the precise load control is the uRLLC scenario, and the same slice scenario cannot be used.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.