HP Building HPE Hybrid IT Solutions (Rev. 19.41) HPE0-V14 Question # 61 Topic 7 Discussion

HP Building HPE Hybrid IT Solutions (Rev. 19.41) HPE0-V14 Question # 61 Topic 7 Discussion

HPE0-V14 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

A solution integrator is installing new data center components including an HPE G2 Advanced Rack with two Standard Series G2 PDUs A customer observing the installation process questions whether there will be sufficient power for additional equipment that may be added in the future.

How should the solution integrator respond?


A.

HPE G2 Advanced racks allow additional PDUs to be added if additional equipment requires more outlets or more available power


B.

HPE Standard Series G2 PDUs allow additional inlet power cords to support additional equipment in the future.


C.

HPE PDUs support elevated temperatures up to 75°C (1673F), in case the additional equipment power draw results in increased heat generation.


D.

Two HPE Standard G2 PDUs will support 42U of racked equipment, so any equipment added in the future will be accommodated by the current PDU configuration