CInP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

First-Level E&S Teams do two key things that are critical to driving the business' InMS. The second of these is to drive and facilitate __________ for choosing those ideas and opportunities that will ultimately be converted into new innovation projects.

Select one correct answer from the list


A.

the predictive analytics


B.

the coin toss process


C.

the selection process


D.

the evaluation process