GIAC Systems and Network Auditor GSNA Question # 37 Topic 4 Discussion

GIAC Systems and Network Auditor GSNA Question # 37 Topic 4 Discussion

GSNA Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

Which of the following are the goals of risk management? (Choose three)


A.

Identifying the risk


B.

Assessing the impact of potential threats


C.

Finding an economic balance between the impact of the risk and the cost of the countermeasure


D.

Identifying the accused