GIAC Certified Project Manager Certification Practice Test GCPM Question # 87 Topic 9 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 87 Topic 9 Discussion

GCPM Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

Which of the following techniques is described in the statement below?

"It is used to verify whether a particular work can best be accomplished by the project team or must be purchased from outside sources."


A.

Contract type


B.

Expert judgment


C.

Make-or-Buy analysis


D.

Risk analysis