GIAC Certified Project Manager Certification Practice Test GCPM Question # 65 Topic 7 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 65 Topic 7 Discussion

GCPM Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?


A.

1.23


B.

$524,000


C.

.80


D.

100 percent because the vendor caused her lateness


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.