GIAC Certified Project Manager Certification Practice Test GCPM Question # 53 Topic 6 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 53 Topic 6 Discussion

GCPM Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

In which of the following processes is it ensured that the human resources are available and the required team is obtained for completing the project assignments?


A.

Acquire Project Team


B.

Develop Human Resource Plan


C.

Develop Project Team


D.

Manage Project Team


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.