Question #: 53
Topic #: 6

In which of the following processes is it ensured that the human resources are available and the required team is obtained for completing the project assignments?


A.

Acquire Project Team


B.

Develop Human Resource Plan


C.

Develop Project Team


D.

Manage Project Team


Get Premium GCPM Questions