GIAC Certified Project Manager Certification Practice Test GCPM Question # 51 Topic 6 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 51 Topic 6 Discussion

GCPM Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

Which of the following is a key input to the processes within the project?


A.

Closing


B.

Code of Accounts


C.

Claim


D.

Contract


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.