GCPM Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

You work as a project manager for PassGuide Inc. You have to subdivide project deliverables and project work into smaller, more manageable components. Which of the following processes will you use to perform the above task?


A.

Control scope


B.

Verify scope


C.

Create WBS


D.

Define activities