GCPM Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

Jane works as a project manager for PassGuide Inc. The project on which Jane is working will last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?


A.

Throughout the project


B.

Only once, at the beginning of the project


C.

Throughout the executing processes


D.

Once per project phase


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.