GIAC Certified Project Manager Certification Practice Test GCPM Question # 30 Topic 4 Discussion
GCPM Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4
Jane works as a project manager for PassGuide Inc. The project on which Jane is working will last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?