GIAC Certified Project Manager Certification Practice Test GCPM Question # 23 Topic 3 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 23 Topic 3 Discussion

GCPM Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Which of the following documents is described in the statement below?

"It is a companion document to the WBS. It describes each component in the WBS. It includes a brief definition of the scope or statement of work, defined deliverables, a list of associated activities, and a list of milestones. It details all work packages in WBS including estimates and billing information."


A.

WBS dictionary


B.

Contract


C.

Project charter


D.

Activity list


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.