GIAC Certified Project Manager Certification Practice Test GCPM Question # 90 Topic 10 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 90 Topic 10 Discussion

GCPM Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

Which of the following processes is described in the statement below?

"It is the process of identifying the specific actions to be performed to produce the project deliverables."


A.

Define Activities


B.

Create WBS


C.

Define Scope


D.

Sequence Activities