GIAC Certified Project Manager Certification Practice Test GCPM Question # 7 Topic 1 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 7 Topic 1 Discussion

GCPM Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

Which of the following is described in the statement below?

"It is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project."


A.

WBS


B.

RBS


C.

Gantt chart


D.

Critical path