GIAC Certified Project Manager Certification Practice Test GCPM Question # 1 Topic 1 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 1 Topic 1 Discussion

GCPM Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?


A.

$306,000


B.

.75


C.

.94


D.

$344,250


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.