New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

GIAC Certified ISO-2700 Specialist Practice Test G2700 Question # 110 Topic 12 Discussion

GIAC Certified ISO-2700 Specialist Practice Test G2700 Question # 110 Topic 12 Discussion

G2700 Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

Which of the following indicates that the project team has decided not to change the project management plan to deal with a risk?


A.

Risk avoidance


B.

Risk mitigation


C.

Risk transference


D.

Risk acceptance


Get Premium G2700 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.