CLSSGB Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:

Data:

Cutting38

Forming17

Stitching56

Sealing42


A.

Forming, Sealing, Cutting, Stitching


B.

Sealing, Stitching, Forming, Cutting


C.

Stitching, Sealing, Cutting, Forming


D.

Forming, Cutting, Sealing, Stitching