GAQM Certified Lean Six Sigma Green Belt (CLSSGB) CLSSGB Question # 49 Topic 5 Discussion
CLSSGB Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5
Training cost $6,500 and a project required an initial investment of $47,500. If the project yields monthly savings of $3,500 beginning after 4 months, what is the payback period in months, before money costs and taxes?