GAQM Certified Lean Six Sigma Black Belt (CLSSBB) CLSSBB Question # 50 Topic 6 Discussion

GAQM Certified Lean Six Sigma Black Belt (CLSSBB) CLSSBB Question # 50 Topic 6 Discussion

CLSSBB Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

A team working with a plant relocation is tasked with designing a process for moving 180 pieces of equipment. Incoming orders may need to be filled during the move at either the old site or the new one. Transportation equipment availability is uncertain. Construction schedules at the new site is very weather dependent. The team designs a chart that attempts to cover these and other contingencies with appropriate measures dealing with each.

The tool best fitted for this task is:


A.

Affinity diagram


B.

Inter-relationship digraph


C.

Tree diagram


D.

Process decision program chart


E.

Matrix diagram


F.

Prioritization matrix


G.

Activity network diagram