GAQM Certified Lean Six Sigma Black Belt (CLSSBB) CLSSBB Question # 33 Topic 4 Discussion

GAQM Certified Lean Six Sigma Black Belt (CLSSBB) CLSSBB Question # 33 Topic 4 Discussion

CLSSBB Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:


A.

inform all concerned that the entire project will be delayed by 20%


B.

inform all concerned that the entire project will be delayed but by less than 20%


C.

study the effect this will have on other activities because the project may still be on schedule


Get Premium CLSSBB Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.