The Product Owner’s primary accountability is maximizing the value of the product, per theScrum Guide. Metrics should reflect outcomes, not just internal process efficiency:
A (Time to market):Faster delivery of Increments to the market validates value through real-world feedback, a key Scrum principle.
B (Customer satisfaction):This directly measures whether the product meets user needs, aligning with value delivery.
C (Velocity):While useful for Developers to gauge capacity, it’s an internal metric, not adirect indicator of value.
D (Productivity):This focuses on effort, not outcome, and isn’t tied to value in Scrum.
[Reference:Scrum Guide(2020), Section: "The Product Owner.", ]