TheScrum Guidestates: "The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team" and for "developing and explicitly communicating the Product Goal." This makes them the primary person responsible for tracking progress toward business objectives or releases, as they align the Product Backlog with stakeholder needs and strategic goals. Option B (Developers) focuses on Sprint-level execution, not overarching objectives. Option C (Scrum Master) ensures process adherence, not business progress. Option D (Project Manager) isn’t a Scrum role. Thus, A is correct.
[Reference:Scrum Guide(2020), Section: "The Product Owner.", ]