GAQM Associate in Project Management (APM) APM-001 Question # 75 Topic 8 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 75 Topic 8 Discussion

APM-001 Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

Which tool or technique is used in the Develop Project Management Plan process?


A.

Pareto diagram


B.

Performance reporting


C.

SWOT analysis


D.

Expert judgment