GAQM Associate in Project Management (APM) APM-001 Question # 73 Topic 8 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 73 Topic 8 Discussion

APM-001 Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?


A.

0.50


B.

0.67


C.

1.50


D.

2.00


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.