Requirements documentation will typically contain at least:


A.

Stakeholder requirements, staffing requirements, and transition requirements.


B.

Business requirements, the stakeholder register, and functional requirements.


C.

Stakeholder impact, budget requirements, and communications requirements.


D.

Business objectives, stakeholder impact, and functional requirements.