Which action is included in the Control Costs process?
Identify how the project costs will be planned, structured, and controlled
Determine policies, objectives, and responsibilities to satisfy stakeholder needs
Develop an approximation of the monetary resources needed to complete project activities
Monitor cost performance to isolate and understand variances from the approved cost baseline