GAQM Associate in Project Management (APM) APM-001 Question # 30 Topic 4 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 30 Topic 4 Discussion

APM-001 Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

Which action is included in the Control Costs process?


A.

Identify how the project costs will be planned, structured, and controlled


B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs


C.

Develop an approximation of the monetary resources needed to complete project activities


D.

Monitor cost performance to isolate and understand variances from the approved cost baseline


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.