APM-001 Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?


A.

Strong


B.

Weak


C.

Managed


D.

Balanced