Which describes a CORRECT approach to change authorization?
Changes included in the change schedule are pre-authorized and do not need additional authorization
formal changes should be assessed and authorized before they are deployed
Emergency changes should be authorized by as many people as possible to reduce risk
formal changes are typically implemented as service requests and authorized by the service desk