EMC Backup and Recovery - Avamar Specialist Exam for Implementation Engineers E20-594 Question # 16 Topic 2 Discussion

EMC Backup and Recovery - Avamar Specialist Exam for Implementation Engineers E20-594 Question # 16 Topic 2 Discussion

E20-594 Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Which is the last step in the hardware installation portion of an EMC Avamar multinode deployment?


A.

Connecting to the customer network


B.

Cabling the nodes to the switch


C.

Powering on the nodes


D.

Placing nodes in the rack